It seems our volunteers for the Camp Chamisol Project
just cant get enough!
Two more work days are scheduled for December!
DATE: December 27, December 29 2007
LOCATION: Waiparous - Camp Chamisol
TIME: 10:00
Meeting Place: Just past Camp Howard
What To Bring:
Chainsaw
UPDATED. DEC.7.2007
Due to the Christmas season -
maybe even the cold weather ;) - volunteer
Project Coordinators have decided to postpone any projects for the month of
December! They will begin completion of the Camp Chamisol project sometime
in January, weather pending!
Thank you to those who have dedicated their time so far towards the project,
and we all look forward to seeing you in the new year!
December 8th and 9th work days CANCELLED
UPDATED.
NOV.30.2007
* This project is expected to take anywhere from two to
three months,
weather pending.
UPCOMING WORK DAYS: December 1st, 2007 AND December 8th, 2007 AND
December 9th 2007
MEETING LOCATION: Just past Camp Howard
TIME: 10:00am
PROJECT CONTACT: Kevin Novakowski: (kevin.novakowski@gmail.com)
Gary Salekin: (sale1@telusplanet.net)
Alberta Projects: (
alberta.projects@gmail.com)
2 - 4 trucks are required to skid out the trees and at least 6 volunteers
are needed.
This project is moving along pretty fast - but we need more volunteers as
the weather will only get colder!
The sooner this project gets completed, the sooner a new road will be built
and access granted!
Approval has been given to begin clearing the right of way around Camp
Chamisol.
Volunteers are needed to clear approx 1KM X 8m of road.
Most trees are no more then 6inches in diameter and will have to be hauled
out.
Spray Lakes has waived their right to the salvage so the posts and rails can
be used in future projects.
Tops and limbs can be burned on site depending on ground conditions.
The stumps will be used for controlling traffic on the other trails in the
area.
NOTE:
Hard hats, steel toe boots, safety glasses and chaps must
be worn!!
ATV's and trucks will be needed to haul materials out of the project site
and to the MS Camp.
What to bring:
Lunch, water, work gloves, warm clothing and chainsaw
START DATE: November 10th 2007
(Project will span over a few weekends until complete)
TIME: 10:00am
MEETING LOCATION: Between Camp
Howard and Camp Chamisol
PROJECT CONTACT: Gary Salekin
(sale1@telusplanet.net)
If you are able to volunteer for this project,
please confirm your attendance at
alberta.projects@gmail.com
|
PROJECT UPDATE:
- November 24th
5 volunteers came out for the day to clear out approx. 300
feet of road.
- November 18-20th
Second, third and fourth work days are complete.
Approx 800 feet of new road
has been cut. Some is still waiting
to be cleared from the road.
- November 10th
The first day of this project has been completed. Approx 300
feet of road
has been cleared.
|